"SB-100, SE-135 possible structure fire: 125 Freedom Drive, Box 1125" At around 19:20 EST, a call was received about a structure fire. Battalion 100 and SE-135 were dispatched first. Upon arrival Chief Studsky did a 360 and spoke with the owner, who states the fire was caused by a faulty welder, this led to a chain reaction that set off explosions in the pressurized shielding gas tanks. Meanwhile the 3 man crew of SE-135 are pulling 2 attack lines and preparing for an offensive attack. "SB-100 to COMM, confirmed structure fire, requesting SE-112 and SR-115" While attacking the blaze, SE-135's crew is backed up by the arrival of SE-112 and SR-115, SR-115 provides RIT support and extra equipment, while SE-112 provides extra manpower for the offensive attack. "SB-100 to COMM, under control, starting overhaul" After a quick knockdown, the crews start overhaul and clean up, clearing the scene a half hour later.
0 Comments
Leave a Reply. |
Click that little orange button to subscribe, and get updates on this blog!
Archives
May 2021
|